Two project managers have just realized that they are in a weak matrix organization and that their power as project managers is quite limited. One figures out that he is really a project expediter and the other realizes he is really a project coordinator. How is a project expediter different from a project coordinator?
A、The project expediter cannot make decisions.
B、The project expediter can make more decisions.
C、The project expediter reports to a higher-level manager.
D、The project expediter has some authority.

试题出处:http://www.ruantiku.com/shiti/3546112564.html
在下面提交答题后即可查看答案与考友试题分析

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!