未指定试题:themethodofcalculatingtheeacbyaddingther

2017年11月06日

试题来源:信管网 作者:cnitpm

试题分类:未指定

The method of calculating the EAC by adding the remaining project budget (modified by a performance factor) to the actual to date is used most often when the
A、Current variances are viewed as atypical ones
B、Original estimating assumptions are no longer reliable because conditions have changed
C、Current variances are viewed as typical of future variances
D、Original estimating assumptions are considered to be fundamentally flawed

试题出处:http://www.ruantiku.com/shiti/352971145.html