A project is a week behind schedule because an engineer is not familiar with some of the technology. The project manager assigns a senior resource to mentor the engineer and documents it in the project management plan. This is an example of which of the following ?
A、Work performance information.
B、 Expert judgment.
C、 Corrective action.
D、 Preventive action.