信息系统项目管理师每日一练试题内容(2025/7/13)
试题1
The strategies for handling risk comprise of two main types:negative risks, and positive risks.The goal of the plan is to minimize threats and maximize opportunities.When dealing with negative risks,there are three main response strategies( ),Transfer ,Mitigate .
A.Challenge
B.Exploit
C.Avoid
D.Enhance
查看答案
试题参考答案:C
试题2
根据软件生存周期标准,验证确认过程属于()。查看答案
试题参考答案:B
试题3
在政府采购工作中,不符合政府采购法相关规定的是:()。查看答案
试题参考答案:D
试题4
Xinhua News Agency reported in January 2022,China will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ()transformation.查看答案
试题参考答案:A
试题5
( )provides guidance for the development and improvement of capabilities for introducing new and changed service into supported environment.查看答案
试题参考答案:B
试题6
质量保证成本属于质量成本中的()成本。查看答案
试题参考答案:A
试题7
多个项目需要同一资源,否则便不能实施。为使延迟的项目数最少,应将该资源优先分配给( )
A、总时差最短的项目
B、历时最短的项目
C、计划开始最早的项目
D、计划结束最晚的项目
查看答案
试题参考答案:A
试题8
某信息系统集成项目计划6周完成,项目经理就前4周的项目进展情况进行分析情况如下,项目的成本执行指数CPI为()。
查看答案
试题参考答案:A
试题9
《计算机信息系统安全保护等级划分准则》规定了计算机系统安全保护能力的5个等级。其中,按照()的顺序从左到右安全能力逐渐增强
A、系统审计保护级、结构化保护级、安全标记保护级
B、用户自主保护级、访问验证保护级、安全标记保护级
C、访问验证保护级、系统审计保护级、安全标记保护级
D、用户自主保护级、系统审计保护级、安全标记保护级
查看答案
试题参考答案:D
试题10
某集成企业把部分集成项目分包出去,准备采用竞争性谈判方式。以下叙述不正确的是( )。
A.竞争性谈判的结果主要依据供应商的综合实力确定
B.应先确立一个标准,然后按照标准进行竞争性谈判
C.可先从合格供应商数据库中筛选供应商,再进行竞争性谈判
D.进行竞争性谈判时,选择供应商的基本原则是一致的
查看答案
试题参考答案:A