  • 试题1

    The (1) process differs from the (2) process in that the former is primarily concerned with acceptance of the deliverables,while the latter is primarily concerned with correctness of the deliverables.
    (1)A. Perform Quality Assurance
    B. Validate Scope
    C. Control Quality
    D. Define Scope
    (2)A. Perform Quality Assurance
    B. Validate Scope
    C. Control Quality
    D. Define Scope

    查看答案

    试题参考答案:B、C

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=1&day=2025/3/17

  • 试题2

    项目范围基准包括()
    A、批准的项目范围说明书、WBS及WBS字典
    B、项目范围说明书、WBS及WBS字典
    C、项目范围说明书、WBS
    D、批准的项目范围说明书、WBS

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=1&day=2025/3/17

  • 试题3

    项目管理过程5个过程组可以对应到PDCA循环中,()过程组与PDCA循环中的检查和行动相对应。
    A、规划
    B、执行
    C、监控
    D、收尾

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=1&day=2025/3/17

  • 试题4

    在信息系统开发某个阶段工作结束时,应将工作产品及有关信息存入配置库的( )。
    A.受控库
    B.开发库
    C.产品库
    D.知识库

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=1&day=2025/3/17

  • 试题5

    团队成员的离职率降低,是()过程的输出。
    A、规划资源管理
    B、管理团队
    C、建设团队
    D、控制资源

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=1&day=2025/3/17

  • 试题6

    Estimating schedule activity costs involves developing an(1 )of the costs of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. For example, in most application areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations. The cost estimating process considers whether the expected savings can offset the cost of the additional design work. Cost estimates are generally expressed in units of     (2 )to facilitate comparisons both within and across projects. The(3 )describes the business need, justification, requirements, and current boundaries for the project. It provides important information about project requirements that is considered during cost estimating.
    (1)A. accuracy        B. approximation       C. specification       D. summary
    (2)A. activity         B. work                C. currency           D. time
    (3)A. project scope statement
    B. statement of work
    C. project management plan
    D. project policy

    查看答案

    试题参考答案:B、C、A

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=1&day=2025/3/17

  • 试题7

    某公司的组织结构如下图所示,该公司采取的是( )组织结构。

    A、强矩阵型
    B、职能型
    C、弱矩阵型
    D、项目型

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=1&day=2025/3/17

  • 试题8

    项目沟通管理是确保及时、正确地产生、收集、分发、()和处理项目信息所需的过程。
    A.存储
    B.分析
    C.接收
    D.分享

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=1&day=2025/3/17

  • 试题9

    关于识别干系人过程的描述,不正确的是()
    A.干系人登记册是识别干系人过程的主要输出,记录已识别干系人的信息
    B.变更日志、问题日志、需求文件可以作为识别干系人过程的输入
    C.对干系人进行分类的方法,包括权力利益方格、因果图、回归分析、凸显模型等
    D.识别干系人的主要作用是使项目团队能够建立对每个干系人或干系人群体的适度关注

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=1&day=2025/3/17

  • 试题10

    在国家标准GB/T 8567-2006《计算机软件文档编制规范》中,将系统需求分成三大类,分别是()。
    A、功能需求、业务需求和数据需求
    B、接口需求、资源需求和数据需求
    C、功能需求、接口需求和安全需求
    D、业务需求、配置需求和维护需求

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/exam/ExamDay.aspx?t1=1&day=2025/3/17