试题1
招标投标是一种国际惯例,是一种()行为。查看答案
试题参考答案:D
试题2
()The process of determining,documenting, and managing stakeholder needs and requirements to meet Project objectives
A、 Plan Scope Management
B、 Collection Requirements
C、 Validate Scope
D、 Control Scope
查看答案
试题参考答案:B
试题3
() includes the processes required to ensure that the project includes all the work required , and only the work required , to compete the project successfully . Managing the project scope is primarily concerned with defining and controlling what is not included in the project.查看答案
试题参考答案:C
试题4
()is a document generated by the creating WBS process that support the WBS,which provides more detailed descriptions of the components in the WBS.查看答案
试题参考答案:C
试题5
()is a grid that shows the project resources assigned to each work package.查看答案
试题参考答案:D
试题6
The key benefit of the Project () is that it determines whether to acquire goods and services from outside the project, if so, what to acquire as well as how and when to acquire it .查看答案
试题参考答案:D
试题7
PDM includes four types of dependencies or precedence relationships
…
( ). The completion of the successor activity depends upon the initiation of the predecessor activity.
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
查看答案
试题参考答案:D
试题8
以下关于类和对象关系的叙述中,( )是不正确的
A、对象是类的实例
B、类是对象的抽象
C、类是静态的,对象是动态的
D、类和对象必须同时存在
查看答案
试题参考答案:D
试题9
The project team members should also be aware of one of the fundamental tenets of modern quality management: quality is planned ,designed and built in, not ( ).
A. executed in
B. inspected in
C. check-in
D. look-in
查看答案
试题参考答案:B
试题10
During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may, however, want to track appropriate measures of requirements volatility to judge whether new or revised ( )are necessary.
A. proceedings
B. controls
C. forecasting’s
D. prelibations
查看答案
试题参考答案:B