  • 试题1

    During the project, requirements change for a variety of reasons. As needs change and as work proceeds, additional requirements are derived and changes may have to be made to the existing  requirements. It is essential to manage these additions and changes efficiently and effectively. To effectively analyze the impact of the changes, it is necessary that the source of each requirement is known and the rationale for any change is documented. The project manager may,  however, want  to  track appropriate measures  of requirements volatility to judge whether new or revised ( )are necessary.
    A. proceedings
    B. controls
    C. forecasting’s
    D. prelibations

  • 试题2

    UML2.0中共包括14种图,其中()属于交互图。
    A、类图
    B、定时图
    C、状态图
    D、对象图
  • 试题3

    数据价值化是指以()为起点,经历数据资产化,数据资本化的阶段,实现数据价值化的过程。
    A.数据智能化
    B.数据资源化
    C.数据安全性
    D.数据产业化

信息系统项目管理师每日练习题答案解析(2023/8/27)

  • 试题1

    信管网参考答案B

    信管网参考解析:

    参考译文
        在一个项目的生命期内,有多种原因可以引起对需求的变更。当需要发生变更而工作正在进行时,可导致新的需求产生并迫使现有的需求发生变更。需要快速而有效地管理这些新的需求和新的变更。为了有效地分析这些变更的影响,必须确定每一个需求源,并记录变更的基本过程。无论如何,项目经理希望能追踪有关需求稳定性的、恰当的措施,以判断是否需要新的或修正的控制措施。

  • 试题2

    信管网参考答案B

    信管网参考解析:

    软题库原题:http://www.ruantiku.com/shiti/32258167.html

    交互图展现了一种交互,它由一组对象或参与者以及它们之间可能发送的消息构成。交互图专注于系统的动态视图。

    交互图包括:顺序图、通信图、定时图

    UML 2.0中的图:http://www.cnitpm.com/pm1/48586.html

  • 试题3

    信管网参考答案B

    信管网参考解析:数据价值化是指以数据资源化为起点,经历数据资产化、_数据资本化阶段,实现数据价值化的经济过程。