系统规划与管理师英语题真题考点:变更管理(Change management)
变更管理通常由变更的提出和记录、评估提议变更的影响、成本、效益和风险、开发业务理由和获得批准、管理和协调变更实施、监测和报告实施组成,审查和关闭和更改请求。
考点相关真题
Change management would typically be composed of the raising and recording of changes, assessing the impact, cost, benefit and risk of proposed changes,developing business justification and obtaining approval, managing and coording change implementation, monitoring and reporting on implementation, reviewing and closing ().
A、change reason
B、change model
C、remediation plan
D、change requests
查看答案
参考答案:D