2023年07月05日来源:信管网 作者:cnitpm
信息系统项目管理师每日练习题(2023/7/5)
试题1
Many of the activities performed during the preliminary investigation are still being conducted in(1 ), but in much greater depth than before. During this phase, the analyst must become fully aware of the(2 ) and must develop enough knowledge about the(3 ) and the existing systems to enable an effective solution to be proposed and implemented. Besides the(4 ) for process and data of current system, the deliverable from this phase also includes the(5 ) for the proposed system.
(1)A. analysis phase
B. design phase
C. implementation phase
D. maintenance phase
(2)A. main symptom
B. root problem
C. final blueprint
D. data specification
(3)A. hardware environment
B. testing environment
C. software environment
D. business environment
(4)A. logical models
B. physical models
C. design models
D. implementation models
(5)A. hardware and software specification
B. system performance specification
C. formal requirements definition
D. general problem statement
试题2
项目经理有责任处理项目过程中发生的冲突,以下解决方法中,()会使冲突的双方最满意,也是冲突管理最有效的一种方法。
A、双方沟通,积极分析,选择合适的方案来解决问题
B、双方各作出一些让步,寻求一种折中的方案来解决问题
C、将眼前的问题搁置,等待合适的时机再进行处理
D、冲突的双方各提出自己的方案,最终听从项目经理的决策
试题3
在信息系统的生命周期中,开发阶段不包括()。信息系统项目管理师每日练习题答案解析(2023/7/5)
试题1
信管网参考答案:A、B、D、A、C
信管网参考解析:
参考译文:在初步调研时完成的许多活动在分析阶段还要继续进行,只是比以前更深入地去做。在这个分析阶段,系统分析师一定要充分注意到问题的根源,并且充分掌握关于业务环境和现行系统的知识,以提交和实施一个有效的解决方案。除了提交现行系统的过程和数据的逻辑模型外,这一分析阶段的交付物还包括推荐系统的正式需求定义。
试题2
信管网参考答案:A
信管网参考解析:
冲突管理最有效的方法就是问题解决。
冲突管理的方法:http://www.cnitpm.com/pm/12308.html
试题3
信管网参考答案:A
信管网参考解析:信息系统的生命周期还可以简化为立项(系统规划)、开发(系统分析、系统设计、系统实施)、运维及消亡四个阶段,在开发阶段不仅包括系统分析、系统设计、系统实施,还包括系统验收等工作。如果从项目管理的角度来看,项目的生命周期又划分为启动、计划、执行和收尾4个典型的阶段。
信息系统的生命周期:https://www.cnitpm.com/pm1/49496.html
温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!