71、Any one or any group of activities utilizing resources totransfer input into output can be viewed as a ()。【转自信管网(cnitpm.com)】

A、system

B、structure

C、procedure

D、process

参考答案:D

72、The process control charts are used ()。【转自信管网(cnitpm.com)】

A、to graph what typically focuses on the prevention of a problem

B、to detect the problem

C、to reject the problem

D、to determine the acceptability of the sample

参考答案:B

73、The IT service manager has learned that a software canimprove the efficiency of current and future project tasks. Because the software is fresh to the Company. Theengineer is not familiar with the software. The lT service manager decides to send the highest level engineero attend the external training course. The proiect manager uses () risk strategies。

A、mitigation【转自信管网(cnitpm.com)】

B、enhancement

C、development

D、sharing

参考答案:A

74、()is closet to Deming's definition of Quality。

A、Conformance to requirements【转自信管网(cnitpm.com)】

B、Fitness for use

C、Continuousimprovement of products and services

D、Customer focus

参考答案:C

75、The IT service manager resigns from a project that meets the scheduleand budget. After hiring an alternativenew manager, the team is opposed to the comments from the new manager. The team is at () developmentstages。【转自信管网(cnitpm.com)】

A、Forming

B、Storming

C、Norming

D、Performing

参考答案:A