2023年05月16日来源:信管网 作者:cnitpm
PMP®当天每日一练试题地址:www.cnitpm.com/exam/ExamDay.aspx?t1=33
往期PMP®每日一练试题汇总:www.cnitpm.com/class/27/e33_1.html
PMP®每日一练试题(2023/5/15)在线测试:www.cnitpm.com/exam/ExamDay.aspx?t1=33&day=2023/5/15
点击查看:更多PMP®习题与指导
PMP®每日一练试题内容(2023/5/15)
试题1
一个组织正在从预测性项目管理过渡到敏捷。作为项目经理,你即将开展的项目需要提交合规报告,由于监管的原因,这些报告需要提交给内部审计师。如何在这种混合环境中满足法规遵循报告的需要?查看答案
试题参考答案:A
试题2
在为新敏捷项目确定用户故事优先顺序时,产品负责人应重点关注什么?查看答案
试题参考答案:D
试题解析与讨论:www.cnitpm.com/st/528921352.html
试题3
项目管理办公室要求项目经理立即开始项目收尾,以下哪项工作不属于收尾的组成部分?查看答案
试题参考答案:D
试题4
项目的所有可交付成果已经完成,并通过了质量验收,CPI=0.8,SPI=1.2,可交付成果提前给客户测试,客户提出小的变更,怎么办?查看答案
试题参考答案:B
试题5
Two of your team members have been arguing for the past several weeks about which project management software will work best for the project. You are tired of listening to them. So you decide to conduct a meeting to see whether they can r each consensus on the matter by identifying common points of agreement and striving for fair resolution. Which style of conflict resolution will you employ?查看答案
试题参考答案:B
试题6
项目经理正在测量项目绩效,成本绩效指数(CPI)是1.1,卖方提出调整一个工作包的范围,变更没有超出预期,管理层要求对未来这部分范围重新做规划,有三个干系人抱怨会对他们部门产生的影响,最恰当做法是?查看答案
试题参考答案:D
试题7
A new key stakeholder is concerned that the project manager failed to send an important update regarding the project schedule.what should the project manager have followed to prevent this?查看答案
试题参考答案:D
试题解析与讨论:www.cnitpm.com/st/480765336.html
试题8
While working on an important project deliverable,a team m ember informs the project manager that applying a change us ed in a previous project will save time and reduce costs. What should the project manager do next?查看答案
试题参考答案:D
试题9
A project consists of five tasks.-Task A will take five days to complete and can begin immediately.-Task B will take four days to complete,but can begin only after task A has finish ed.-Task C will take three days to complete,and is independent of any other tasks before it can begin.-Task D will take seven days to complete,but can begin only after task C is finished.-Task E will take five days to complete,but can begin only after both tasks B and D have finished. What is the project's critical path ?查看答案
试题参考答案:B
试题10
采用较简单的过程,执行更多测试或选择更加稳定的供应商属于哪种消极风险响应类型?()查看答案
试题参考答案:A
温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!
相关推荐