There is an international collaborative project plan. The project manager is assigned to produce a viable project plan to implement project. The project sponsor says that it may be necessary to crash the project. As the project manager determines the project funding requirements are needed to complete the task?() 某国际合作项目计划制造并向市场投放一种创新工具,项目经理受命对该项目的实施指定可行的项目计划,项目赞助人称,项目可能需要赶工,项目经理在确定项目资金需求时,需要下列哪些辅助以完成任务?() A、Activity cost estimates basis of estimates, scope baseline, project schedule, resource calendars, contracts, and organizational process assets 活动成本估算、估算依据、范围基线、项目进度表、资源日历、合同以及组织过程资产 B、Scope baseline, Stakeholder register,cost performance baseline,schedule baseline register, enterprise environmental factors, and organizational process 范围基线、利害关系者登记簿、成本、绩效基线、进度基线、风险登记簿、企业环境因素和组织过程资产 C、Work performance measurements, budget forecasts,organizational process assets updates, change requests, project management plan updates, and project documents updates 工作绩效评估、预算预测、组织过程、资产更新变更请求、项目管理计划更新和项目文件更新 D、Control threshold, performance measurement,process description, process rates, unit measures, and cost per work breakdown structure measures. 控制界限、绩效评估、过程说明、过程费率单位措施及各工作分解结构措施的成本
You are assigned project manager in executing project;the project is in control on baseline, if customers are not satisfied with the performance, then what you should do firstly? 在项目执行过程中,你被任命为项目经理。项目各项指标都在基线的允许范围内,如果客户对项目绩效不满意,你首先应该做什么? A、Discussing with project team 与项目团队一起讨论 B、Baseline revised 重新计算基线 C、Contract Renegotiation 重新商谈合同 D、Meeting with customers 与客户见面
What diagram is used to illustrate the connections between work to be completed and team resources?() 下列哪一种图表示用来说明需要完成的工作与团队资源之间的关系?() A、Resource histogram 资源直方图 B、Organizational chart 组织图 C、Control chart 控制图 D、RACI chart RACI图
During the execution phase of the project, the project team identified a serious project plan deviation. The scope of the p ro1ect was defined correctly but the planning missed some technical deliverables that have impacted the schedule and the planned cost.In order to assure the success of the project, which should the project manager do? 在项目执行阶段,项目团队识别出了一项严重的项目计划偏差。项目范围定义正确,但是计划却遗漏了一些技术可交付成果,从而影响了进度和计划成本。为确保项目成功,项目经理应该如何作? A、Ask the customer to pay the cost of the deviation 让客户支付偏差的成本 B、Propose a change request, and inform the stakeholder s of this case to get their supports 提交变更请求,通知该情况的相关方,获得他们的支持 C、Negotiate with team to work overtime for mitigating t he impact of cost and schedule 与团队协商,加班工作,减少进度和成本影响 D、Negotiate with customer to reduce the scope of project for avoiding the deviation 与客户协商,减少项目范围,避免偏差