PMP®每日一练试题内容(2023/4/29)
试题1
一家公司正在实施一个在线文档系统,若要执行项目评估,项目经理首先应该做什么?查看答案
试题参考答案:A
试题2
某敏捷项目团队难以商定一次迭代中的后续步骤。团队应该怎么做来达成一致意见?查看答案
试题参考答案:D
试题解析与讨论:www.cnitpm.com/st/530098913.html
试题3
你被委任为一个非常复杂项目的项目经理。因为该项目处于非常关键的位置,高层经理让你立刻开始识别风险并且制定应对策略。组织中虽然有风险管理的流程,但是很少被用过,并且组织之前有过风险管理失败的例子,该项目的下一个重要里程碑节点是两周之内,对你来说,如下哪项对你制定风险应对计划是最没有用的?查看答案
试题参考答案:B
试题4
A vendor communicates that the delivery of a project item w ill be delayed by two weeks.What should the project manage r do?查看答案
试题参考答案:A
试题5
You are the project manager for the construction of a hog rendering plant. Local residents and environmental groups are opposed to this project. They have produced reams of data showing that the volume of entrails and carcasses burned at the site will cause noxious-and possibly toxic-fumes to which the residents will be exposed.They have threatened to take your company to court.You find you are spending most of your time trying to work with these groups to alleviate their concerns.After so much time and effort in these meetings, you convince management to move this project to a different site out side town. This is an example of which of the following risk responses?查看答案
试题参考答案:D
试题6
A project manager is running a company-wide project involv ing different business units.During a planning session,the project manager notices that each unit's specific requirement s are of no interest to other units,which affects the quality of the meeting. What should the project manager use to resolve specific this?查看答案
试题参考答案:C
试题7
项目团队为军方做项目管理,双方签订了保密协议。项目设置了专用的保密计算机和保密U盘,以确保信息安全。谁有权使用这些工具来发布相关的保密信息? ()查看答案
试题参考答案:D
试题8
A project was completed one year ago,and the project manager and resources are assigned to another project. The customer emails the chief operations officer claiming that a deliverable is not within the expected quality level and requests a change to this deliverable. Before responding to the customer, what document should the chief operation officer review first?()查看答案
试题参考答案:B
试题9
在项目实施期间,项目经理与客户和主题专家一起讨论项目需求。客户提出,他们需要在项目中提供相应的培训,项目经理应该将其记为哪项需求?查看答案
试题参考答案:B
试题解析与讨论:www.cnitpm.com/st/48192133.html
试题10
测试总监通知项目经理,没有足够的资源来完成测试需求,由于公司重组项目经理无法聘请新资源。项目经理应该怎么做?查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/46230310.html