一个敏捷团队正在一起做他们的第一个项目。第一次迭代的目标没有实现,并且开发团队的成员之间存在重大分歧。在迭代回顾中,我们发现一些团队成员工作时间不固定,并且在需要他们的时候工作繁忙。敏捷教练本可以做什么不同的事情来防止这种情况? A: 规定团队的标准工作时间 B: 要求职能部门领导介入 C: 没有办法能阻止描述的情况 D: 促进会议建立社会契约 An agile team is working on their first project together. The objectives for the first iteration were missed, and there is significant dissension among the members of the development team. During the iteration retrospective, it is discovered that some team members are working odd hours and have been unavailable when needed. What might the agile coach have done differently to prevent this situation? A.Mandated standard working hours for the team B.Asked the functional leader to intervene C.Nothing could have prevented the situation described D.Facilitated a meeting to establish a social contract
A project's progress is slower than planned and threatens the delivery date. The project manager determines that a key reason for this issue is an unexpected high number of defects found during functional testing that will require rework. What should the project manager have done to prevent this issue? 一个项目的进度比计划的慢,并威胁到交付日期。项目经理确定这个问题的一个关键原因是在功能测试期间发现了大量需要返工的异常缺陷。项目经理应该做些什么来防止这个问题?() A、Used statistical tools to compare the amount of rework in this project with other projects and adjust project deadlines appropriately 使用统计工具比较这个项目与其他项目的返工数量,并适当调整项目期限。 B、Ensured requirements are reviewed and approved by the testing team prior to the start of development 确保需求在开发开始之前由测试团队审查和批准。 C、Arranged a meeting with the project sponsor to consider reducing the project scope 与项目负责人安排了会议,考虑减少项目范围。 D、Mitigated the project deadline risk by outsourcing the development team 通过外包开发团队减轻项目期限风险
After a project review, the project manager asks a summarize of all the incidents and then prioritize the incidents. Which method should be used?() 在一次项目审查后,项目经理咨询风险问题汇总并进行风险优先级排序。此过程需要用到哪种方法?() A、Probability Impact Matrix 概率影响矩阵 B、PERT 三点估算 C、Risk Assessment 风险评估 D、Risk ranking 风险等级