2023年04月13日来源:信管网 作者:cnitpm
PMP®当天每日一练试题地址:www.cnitpm.com/exam/ExamDay.aspx?t1=33
往期PMP®每日一练试题汇总:www.cnitpm.com/class/27/e33_1.html
PMP®每日一练试题(2023/4/12)在线测试:www.cnitpm.com/exam/ExamDay.aspx?t1=33&day=2023/4/12
点击查看:更多PMP®习题与指导
PMP®每日一练试题内容(2023/4/12)
试题1
After the customer accepts the project deliverable,the project manager begins archiving the project documents.Meanwhile the project manager is assigned to a new,highly visible project before closure of the earlier project is complete What should the project manager do查看答案
试题参考答案:B
试题2
A project manager receives a change request. The change request impacts the project schedule. There is uncertainty about who should make the decisions for the change request implementation. which documents need to be updated?查看答案
试题参考答案:D
试题3
项目的经验教训文件表明,在项目过程中的历史资料利用较差。要找到根本原因,用下列哪种工具?查看答案
试题参考答案:A
试题解析与讨论:www.cnitpm.com/st/474368473.html
试题4
下列哪种情况会经常使用到参数估算?查看答案
试题参考答案:B
试题5
项目经理的前老板打电话对项目经理之前的项目表示不满。因为项目投入运营后,设备操作员不理解用户手册的操作说明。项目经理以下哪个过程执行得不够彻底?查看答案
试题参考答案:B
试题6
一家公司启动了一个信息技术服务器开发项目。在风险评估期间,项目团队识别到一项新技术可能降低项目的成本,项目经理计划将一名经验丰富的专家调入团队。这属于哪种风险应对策略?()查看答案
试题参考答案:B
试题7
在一个关键项目的中间阶段,两名团队人成员被分西到另一个项目。由于他们是项目不可替代的资源,会影响项目进度。项目经理应审查下列哪项?查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/498796760.html
试题8
A project is falling behind schedule due to several quality issues that request extensive rework. The project manager's initial review reveals that design changes were the major cause of this rework. What should the project manager do next?查看答案
试题参考答案:A
试题9
你的团队识别了434个风险,其中大部分都是由16个原因导致的,这个项目非常重要以至于发起人表示了强烈的支持。并且用了很长的时间跟其他相关方来研究这些风,险,但是在风险应对规划过程,团队成员发现这些风险很难被缓解,又不能让其他资源来完成,还不能被删除。此时应对风险的方式是什么?查看答案
试题参考答案:A
试题解析与讨论:www.cnitpm.com/st/47570303.html
试题10
项目经理在制定完项目章程后列出了项目所需的人员编制。项目经理向职能经理询问所有确定资源的可用性。职能经理指出目前人员紧张,难以调配所需资源。项目经理首先应该完成什么?查看答案
试题参考答案:B
试题解析与讨论:www.cnitpm.com/st/498369394.html
温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!