PMP®每日一练试题内容(2023/3/20)
试题1
After a recent company board meeting,stakeholders have changed their product vision and re-established project goals. What should the agile team lead do to communicate these changes to the team?查看答案
试题参考答案:D
试题2
一个进展顺利的项目开始错过一些交付日期,项目经理确定,在制定项目进度计划时,并未考虑到团队成员的休假计划,若要避免这个问题,在规划项目时,项目经理应该事先做什么?查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/462435465.html
试题3
如果项目团队工作的地点不在同一个物理位置上,被称为是虚拟团队或组织结构,这将给团队的沟通带来很大的困难,面对虚拟团队,项目经理应该:查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/423603846.html
试题4
After reviewing team members' skill profiles, the project manager determines specific required skills are missing. What should the project manager do to address this situation?()查看答案
试题参考答案:A
试题5
A manufacturer is experiencing a large number of returned it ems due to production line errors and defects. The product manager suspects that the root causes may be training and/or p oor inventory purchasing and sorting processes.Which to should be utilized to determine the precise root causes of the production problems?查看答案
试题参考答案:D
试题6
A consulting firm was awarded a mega credit card processing system revamping project. Having failed to deliver the expected product within budget the last two mega projects.what approach should the consulting firm take in the initial stages of the project to avoid past failures?()查看答案
试题参考答案:C
试题7
During the project,a team member tells you that a major risk identified by the team has occurred.However.it is not as serious as previously thought.What is the FIRST thing you should do?查看答案
试题参考答案:C
试题8
After identifying all tasks to be carried out in the project, the project manager allocates the tasks to each team member based on their skills. The project manager refers to which of the following documents?查看答案
试题参考答案:C
试题9
To create a project schedule, a project manager estimates resource constraints. Pro1ect team members work various hours and follow different holidays. Different members are assigned to multiple projects. To better understand resource constraints and impacts to the project. what should the project manager do?()查看答案
试题参考答案:A
试题10
An approved project change will require dedicated resources from an IT department. The resource's manager is unavailable to provide approval,but the resource is needed immediately to ensure that the project stays on schedule. What should the project manager do?查看答案
试题参考答案:B