  • 试题1

    在迭代的中途,敏捷团队遇到了一个小的技术问题。其中一位团队成员回忆说,敏捷教练从她过去作为高级开发人员的经验来看,是这个领域的专家。团队要求教练帮助解决这个问题。敏捷教练首先应该做什么?
    A: 让团队解决问题
    B: 帮助团队解决问题
    C: 为团队解决问题
    D: 咨询产品负责人
    Midway into an iteration, an agile team faces a minor technical issue. One of the team members recalls that the agile coach is an expert in the field from her past experience as a senior developer. The team requests that the coach help resolve the issue. What should the agile coach do first?
    A.Let the team resolve the issue
    B.Help the team resolve the issue
    C.Resolve the issue for the team
    D.Consult with the product owner

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/5254629184.html

  • 试题2

    项目经理根据交付约定项目范围所需的能力来确定项目团队成员候选,项目经理接下来应该怎么做?
    A、与职能经理协商谈判,为项目分配资源
    B、与确定的资源协商上其加入项目
    C、立即将资源需求上报给项目发起人
    D、将能力需求更新到风险管理日志中

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/4734929386.html

  • 试题3

    A two-year project is approved and subcontracted for deliver y. During the execution phase, there is a conflict with deliverables from the contractor to the customer. What should the project manager do next?
    一个为期两年的项目获得批准,分包交付。在执行阶段,承包商与客户之间的交付存在冲突。项目经理接下来应该做什么?
    A、Meet with the stakeholders. 与干系人开会。
    B、Verify the procurement agreement. 核实采购协议。
    C、Validate the scope document. 验证范围文档。
    D、Review the procurement plan. 审查采购计划。

    查看答案

    试题参考答案:B

    试题解析与讨论:www.cnitpm.com/st/4886429293.html

  • 试题4

    一个需求定义很充分的采购,项目经理最好使用以下何种合同类型∶
    A、固定总价合同
    B、工料合同
    C、成本补偿合同
    D、一次付款合同

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/4740415601.html

  • 试题5

    某个新项目将使用特定软件发布,在项目启动大会上,一名团队成员记起在之前的一个项目他们已经使用了该软件工具的一版,但该软件造成许多问题,该项目经理接下来应该怎么做?
    A、项目团队成员解释说,自上一个项目后,技术已经发生了很大变化,以后不会发生问题
    B、查看过往项目的经验教训说明,识别新项目中的类似风险
    C、立即将潜在风险上报给项目发起人,以便能够获得额外的资金
    D、结束项目并收集经验教训,让未来的项目可以从该经验教训中获益

    查看答案

    试题参考答案:B

    试题解析与讨论:www.cnitpm.com/st/4771418224.html

  • 试题6

    关于产品生命周期的说法,正确的是:
    A、一个项目生命周期包括若干个产品生命周期 
    B、项目生命周期等同于产品生命周期
    C、项目生命周期和产品生命周期相互独立,产品可能由项目产生
    D、产品生命周期过程包括启动、规划、执行、监控、收尾

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/st/4232725208.html

  • 试题7

    A project manager suspects there is a quality defect in a recently produced batch of products.However, a test for this defect will be destructive to the products. What should the company do next?
    项目经理怀疑最近生产的一批产品存在质量缺陷,对这种缺陷的测试将对产品造成破坏。公司接下来要做什么?
    A、Execute a design of experiments on the batch of products. 在批产品上进行实验设计。
    B、Execute statistical sampling with predefined acceptance criteria.随机从批中选择单元来测量缺陷的程度
    C、Execute statistical sampling with predefined acceptance criteria按照预先定义的验收标准执行统计抽样。
    D、Release the current batch to sell at a discounted price 释放当前批次以折扣价出售。

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/st/4962012073.html

  • 试题8

    A project team member decides that engaging the customer o n some alternative designs is unnecessary if all functionalities are delivered. The entire team decides only to engage the technical department on the designing for best product. After user acceptance testing,the customer complains about the selected design. To ensure that the customer accepts the project deliverables,what should the project manager do?
    一位项目团队成员决定,如果所有功能都已经交付那么让客户参与一些替代设计是不必要的,整个团队决定只让技术部门参与进行最好的产品设计.用户验收测试后,客户对所选的设计有所抱怨.为了确保客户接受项目可交付成果,项目经理应该做什么?
    A、Communicate to the customer that the project design i s determined by the technical team.与客户沟通产品设计是由技术团队决定的
    B、Ask the customer to accept the project deliverables, as they meet all agreed functional requirements. 要求客户接受项目可交付成果,因为它们符合所有约定的功能要求
    C、Ensure that both the customer and technical team collaboratively selects the new product design. 确保客户和技术团队协作选择新产品设计
    D、Update the issues long with the design issue and continue with project execution. 将设计问题更新到问题日志中并继续执行项目

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/st/4805726131.html

  • 试题9

    沟通管理计划的目的是提供有关哪项的信息?
    A、将用于传达信息的方法。
    B、当不需要团队成员时,将其从项目释放的方法。
    C、项目组织和相关方的责任关系。
    D、每名团队成员的经验和技能水平。

    查看答案

    试题参考答案:A

    试题解析与讨论:www.cnitpm.com/st/4926629164.html

  • 试题10

    在项目早期阶段,项目经理意识到项目预算受原材料价格波动的影响。项目经理接下来应该怎么做?()
    A、更新范围说明书
    B、在价格上涨之前采购原材料
    C、更新风险登记册
    D、提出变更请求

    查看答案

    试题参考答案:C

    试题解析与讨论:www.cnitpm.com/st/4916023699.html