2023年02月10日来源:信管网 作者:cnitpm
PMP®当天每日一练试题地址:www.cnitpm.com/exam/ExamDay.aspx?t1=33
往期PMP®每日一练试题汇总:www.cnitpm.com/class/27/e33_1.html
PMP®每日一练试题(2023/2/9)在线测试:www.cnitpm.com/exam/ExamDay.aspx?t1=33&day=2023/2/9
点击查看:更多PMP®习题与指导
PMP®每日一练试题内容(2023/2/9)
试题1
A project manager is tasked with increasing organizational a wareness ofthe company's rebranding project.What should t he project manager do to achieve this?查看答案
试题参考答案:D
试题解析与讨论:www.cnitpm.com/st/478142700.html
试题2
During which project risk management process is risk assessment performed?查看答案
试题参考答案:C
试题3
前两个一直处干正常进度轨道的项目开始经历严重延期。项目经理已经识别到重大问题。项目经理应在哪里报告项目状态?查看答案
试题参考答案:B
试题4
许多问题在向客户展示及发表产品时被提出。由于产品符合要求,敏捷项目团队感到困惑。敏捷管理专业人士应如何缓解这种情况?查看答案
试题参考答案:A
试题5
A consultant company has been awarded a contract to expand an existing facility in a recently populated area. The executives select a project manager and inform them their commitment to support the project and the sensitive nature of the issues. What should be considered firstly by the project manage r?查看答案
试题参考答案:A
试题6
在一次迭代结束时,一位团队成员告诉项目经理,由于几天前出现了无法解决的问题,一个计划任务未完成。若要在将来避免这种情况,项目经理应该怎么做?查看答案
试题参考答案:A
试题解析与讨论:www.cnitpm.com/st/525307991.html
试题7
在制定项目预算时,应该考虑使用下列哪种方法?()查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/489626721.html
试题8
在执行阶段,客户告诉项目经理,三个现有工具的软件版本已更改。现在,三个接口必须以不同方式实施。项目经理应该怎么做?查看答案
试题参考答案:C
试题9
现代质量管理的要求包括了以下所有,除了:查看答案
试题参考答案:C
试题10
During the financial review of the final budget, a financial controller notices a potential cost overrun. How should the project manager do to avoid this potential cost overrun?查看答案
试题参考答案:B
温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!
相关推荐