试题1
During a project's execution phase,the project manager realizes that one vendor has been failing to send status reports.W hat should the project manager do查看答案
试题参考答案:C
试题2
During project execution, the project manager observes that a particular resource is underutilized. Resource leveling aims to do which of the following?查看答案
试题参考答案:A
试题3
审查商业论证后,项目经理下一步应该做什么?查看答案
试题参考答案:C
试题4
A new project manager is developing a project management plan in an area that the project manager has no experience. Which of the following should the project manager reference to benefit from the experience of others?查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/490423213.html
试题5
一家施工公司建筑项目部件采购召开投标人会议。收到投标人的建设书并评审。其中一个供应商提出非常优惠的价格,但是根据内部专家判断,该价格对于开展持续性的业务是不现实的,项目经理接下来该如何做?查看答案
试题参考答案:A
试题6
Two coworkers are developing a project task together. Coworker 1 prefers to write down ideas and thoughts before doing the actual work.Coworker 2 has a direct work style. The difference in their personal work styles creates a conflict between them and affects their performance on project activities. Who is responsible for resolving this issue?查看答案
试题参考答案:A
试题7
制造预期产品原型供相关方进行实验和提供反馈后,项目经理可完成制定下列哪项?查看答案
试题参考答案:B
试题8
The project team has just completed the initial project schedule and budget. The NEXT thing to do is:查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/492597524.html
试题9
生产某个项目可交付成果所需的设备既旧又不可靠,工厂经理建议订购一台新机器。工厂经理向项目经理提交变更请求记录下列哪项?查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/482568606.html
试题10
在项目收尾阶段,项目经理计划开展全面的项目宙查,在转移可交付成果并分发最终项目报告后,项目经理下—步应该怎么做?查看答案