试题分类:英语 ()is a grid that shows the project resources assigned to each work package. A.Stakeholder engagement assessment matrix B.Requirements traceability matrix C.Probability and impact matrix D.Responsibility assignment matrix 试题出处:http://www.ruantiku.com/shiti/518386929.html 在下面提交答题后即可查看答案与考友试题分析 信管网参考答案:D 信管网解析:进入软题库查看解析 查看更多英语试题>>