试题1
A large-scale agile project has been kicked off to build a new project. Several teams are working simultaneously on new and enhanced features. The project manager faces major scaling challenges to ensure that the different features are created and work in harmony. What should the project manager do t o address this?查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/479807087.html
试题2
哪个过程可用于控制范围蔓延的负面效应∶查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/477188238.html
试题3
在与客户进行接触时,他们表达了对即将研发的新产品的总体构想,并提出由于自身资金的限制,整个项目将分两期进行,第一期产品满足基本办公要求就可以,第二期产品才会增加更多分析功能。客户的这些要求应该被如何处理?()查看答案
试题参考答案:A
试题4
An organization adds a new strategic project,which must be completed by the end of the year.The project is critical to the strategic success of the customer.An idea about the scope,budget,and schedule opinions have already been discussed.What should be included in the project charter?查看答案
试题参考答案:C
试题5
Activity 1 of project A has an external dependency(finish-to -start)from activity 2 of project B.The external dependency was identified as a schedule delay risk for project A. However, the project manager accepts the risk,which causes a delay.After accepting this risk, what should the project manager have done to minimize the impact?查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/489194046.html
试题6
你收到—份报告,表明总体进度绩效指数是1.5。请问你应该如何解读这一信息?查看答案
试题参考答案:A
试题解析与讨论:www.cnitpm.com/st/475086250.html
试题7
A quality assurance team member informs the project manager that 100 defects in the deliverable were found. Therefore, any further work on the project must be discontinued. What should the project manager do next?查看答案
试题参考答案:A
试题8
A project manager is assigned to an existing project and need s to understand the project deliverables. The project manager should refer to which of the following?查看答案
试题参考答案:C
试题9
Which statistical analysis technique could the project manager use to calculate the average outcome when the future scenarios include uncertain results?查看答案
试题参考答案:B
试题解析与讨论:www.cnitpm.com/st/492252959.html
试题10
敏捷团队在迭代中,正在开发一个复杂的产品。在第三次迭代中,产品负责人发现了一个问题。产品负责人应该告诉团队什么?查看答案
试题参考答案:A