PMP®每日一练试题内容(2022/11/18)
试题1
Task A has a cost estimate of US$1,000 and a scheduled completing date of December 30,with a total duration of 10 days, The project manager reviews the project if task on December 30 and it is only 70% complete. The resource assigned to task A has spent US$600 to date.What is the planned value?查看答案
试题参考答案:D
试题解析与讨论:www.cnitpm.com/st/489811891.html
试题2
A project manager works in a team of people with different cultures and languages. Training begins. trust is built and the team members are working together toward project goals. Th e team is in which of the following stages of development?查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/498035893.html
试题3
The customer requests a change to the project that would increase the project risk. Which of the following should you do before all the others?()查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/48373243.html
试题4
在准备一个里程碑审查期间,项目经理首次了解到工程师进行了多项技术改进,项目经理应开展哪一项?查看答案
试题参考答案:C
试题5
To control the schedule,a project manager is reanalyzing the project to predict project duration. She does this by analyzing the sequence of activities with the least amount of scheduling flexibility. What technique is she using?查看答案
试题参考答案:A
试题6
项目经理需要在不对预算产生负面影响的情况下,加速一个进度计划落后的项目,项目经理应使用什么技术?查看答案
试题参考答案:B
试题7
项目经理负责管理为一家公司提供服务的项目,希望将项目风险降至最低,项目经理应该选择哪种合同类型?查看答案
试题参考答案:C
试题8
敏捷项目负责人希望确保产品愿景在整个项目过程中不会在团队成员的脑海中消失。对于敏捷领导者来说,实现这个目标的最佳方式是什么?查看答案
试题参考答案:D
试题解析与讨论:www.cnitpm.com/st/525655940.html
试题9
你向项目出资人提供了项目的成本估算,他对估算不满意,因为他认为价格太高了。他要你削减项目估算的1 5%,你该怎么做?查看答案
试题参考答案:C
试题10
项目团队必须对一个关键资源做出是否录用的决定,项目经理需要考虑多个方面,以下哪个不需考虑?查看答案
试题参考答案:C