试题1
A designer for an engineering consulting company has completes the design and releases it for production. During the deliverable verification process,it is discovered that the design standard was changed,and that the produced deliverable fails to comply with it. What planning process should the project manager have implemented to avoid this issue?查看答案
试题参考答案:D
试题解析与讨论:www.cnitpm.com/st/480499903.html
试题2
A project manager identifies and documents the specific actions that produce project deliverables by breaking down work packages into activities. What document will be produced as a result?查看答案
试题参考答案:C
试题3
发起人和高级管理层指示你进行一个你认为对经济和社会都有很大负面影响的项目。你表达了你的担心,但是各方仍然要求你继续。请问你应该怎么做?查看答案
试题参考答案:B
试题4
A meeting to present. discuss,and approve the project management plan is schedule for tomorrow,but a project sponsor is suddenly unavailable for another week. To prevent a delay in the project's start, what should the project manager do?查看答案
试题参考答案:C
试题5
某项目很可能在三个月内花费40000美元。情况是3个月花费30000美元。最差情况是3个月花费65000美元。若使用贝塔分布来计算,项目的预期成本是多少?()查看答案
试题参考答案:C
试题6
在收集项目需求的过程中,需要以下项目文件的支持,哪个不是项目文件的表示形式:查看答案
试题参考答案:B
试题解析与讨论:www.cnitpm.com/st/424446860.html
试题7
在一次为期六周的迭代中,一名团队成员识别到一个问题。分析之后,团队成员确定将至少需要2周时间来解决这个问题。该名团队成员应该怎么做?查看答案
试题参考答案:B
试题解析与讨论:www.cnitpm.com/st/530132164.html
试题8
项目的工期进展到了一半,实际成本7.5万美元,总预算成本10万美元,项目完成了60%的工作,未来将持续这样的绩效,当前的完工尚需估算是∶查看答案
试题参考答案:B
试题9
以下哪个关于项目经理能力的说法不准确的是∶查看答案
试题参考答案:D
试题10
A manufacture identifies that their production line produces a tool with a 2.5% variance, which is outside acceptable limits.A project manager wants to identify the root cause(s)of the persistent defect.查看答案
试题参考答案:A