试题1
A key user representative involved in product validation activities proposes changes to some tasks and deliverables outlined in the project's methodology.These changes would considerably impact the validation strategy defined during the planning phase.What should the project manager do first?查看答案
试题参考答案:C
试题2
project requires that a feasibility study be conducted for the s ale of products in a new country. What type of contract should the project manager use查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/479306381.html
试题3
An organization is completing a critical milestone during the construction of residential properties. The project is fully sponsored by the government. Ten days prior to completion oft his key project phase, affected community members begin a four-day protest,causing the project to be put on hold.W hat should the project manager do?查看答案
试题参考答案:D
试题解析与讨论:www.cnitpm.com/st/480423658.html
试题4
After a long and frustrating day, your company CEO found himself circling the attendant's booth at the adjacent parking garage in a futile attempt to find his way out of the building (h is limousine driver had taken the day off).He approached the building manager the next day and said he would have his staff design an improved system for vehicle egress and ingress. You are the project manager for this project. You decide to use flow charting to()查看答案
试题参考答案:A
试题解析与讨论:www.cnitpm.com/st/496048259.html
试题5
一名新项目发起人接管一个处于执行阶段的项目。项目发起人要求项目经理停止批准项目资源时间表。相反,发起人将该任务分配给另一名团队成员。若要重新确立控制权,项目经理下一步应该做什么?查看答案
试题参考答案:D
试题解析与讨论:www.cnitpm.com/st/482868700.html
试题6
The project manager must complete the project in the shortest time possible. To do so,the Project manager decides to schedule non-dependent tasks so they occur simultaneously, Which technique is the manager employing?()查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/493849980.html
试题7
在项目环境下,有关沟通的论述哪一个是正确的:查看答案
试题参考答案:B
试题解析与讨论:www.cnitpm.com/st/426412410.html
试题8
A project manager sends out regular status reports to all stakeholders with bulleted lists of project accomplishments,up coming objectives,and and current challenges. However, some stakeholders still complain that they do not and understand the project's status,What should the project manager do?查看答案
试题参考答案:C
试题9
项目经理正在管理价值300万美元,涉及两个供应商的项目,项目即将收尾。需要下列哪项信息?查看答案
试题参考答案:C
试题10
The project sponsor informs a project manager that even tough a completed project was on schedule,within budget, and met scope requirements, the customer is dissatisfied with the final product. What should the project manager have done to avoid this?查看答案
试题参考答案:D
试题解析与讨论:www.cnitpm.com/st/476161114.html