2022年07月11日来源:信管网 作者:cnitpm
PMP®当天每日一练试题地址:www.cnitpm.com/exam/ExamDay.aspx?t1=33
往期PMP®每日一练试题汇总:www.cnitpm.com/class/27/e33_1.html
PMP®每日一练试题(2022/7/10)在线测试:www.cnitpm.com/exam/ExamDay.aspx?t1=33&day=2022/7/10
点击查看:更多PMP®习题与指导
PMP®每日一练试题内容(2022/7/10)
试题1
作为一个项目经理,你在制定一份文档以描述项目可交付成果为满足合同、标准、规格或其它正式强制性文件的要求,而应具备的特征或性能。这份文档也称作∶查看答案
试题参考答案:A
试题2
变更控制委员会批准了对项目进度基准的变更。由于项目的可交付成果将作为公司的新产品上市,运营经理表示不满,怀疑对该变更的审查和批准存在漏洞。你将如何证明该变更是符合正式流程的? ()查看答案
试题参考答案:D
试题3
A project manager is notified that a software developer for a critical section of code will be out of the office for three wee ks. This task is not part of the critical path. What should the project manager do next?查看答案
试题参考答案:B
试题4
You are asked to produce a 10-meterlong tube, and you are producing tubes within the range of 12.1 m,11.98 m,12.12 m, 12.08, etc. This means that:查看答案
试题参考答案:B
试题解析与讨论:www.cnitpm.com/st/496167742.html
试题5
项目在落后于进度一个月的情况下完成.项目经理需要立即获得客户的最终验收,最终验收标准中应包含哪些内容?查看答案
试题参考答案:B
试题6
For a process review, a laboratory uses Lean Six Sigma methodology. Mid-way through the project, an audit is scheduled with an external Lean consultant to ensure that the methodology is applied appropriately. What is this process called?查看答案
试题参考答案:D
试题7
A project manager informs the sponsor that the project is behind schedule. The project sponsor threatens to cancel the project as the sponsor does not want to miss the target completion date. Which of the following techniques should the project manager us to expedite the project?查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/494909247.html
试题8
在一个为期三年的项目中途,任命了一名新项目经理。在第一次团队会议上,新项目经理得知有关洪水的情况,以及洪水可能摧毁设备的风险。项目经理首先应该做什么?查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/470555428.html
试题9
What will the project manager need to consider in preparing a coherent risk management plan?查看答案
试题参考答案:B
试题解析与讨论:www.cnitpm.com/st/492412761.html
试题10
The project has been going relatively well,although there have been some problems with resource availability and the project scope has changed more than was expected. The project is now completing one of its phase.Of all decisions the sponsor must consider during an end-of-phase review meeting,the MOST difficult is:查看答案
试题参考答案:C
温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!
相关推荐