PMP®每日一练试题内容(2022/6/15)
试题1
The project manager checks the scope statement against the work results to ensure consistency.The results should be documented and used by the project manager for which of the following?查看答案
试题参考答案:D
试题2
在第三方供应商交付项目组件后报告发生故障。项目经理在供应商的支持下应用应急计划。为了确保风险应对措施的有效性,项目经理应该怎么做?()查看答案
试题参考答案:B
试题3
有四个项目可供选择,根据如下信息,你选择?查看答案
试题参考答案:D
试题解析与讨论:www.cnitpm.com/st/475123272.html
试题4
A project team is commissioning a project upgrade over the weekend.The client-appointed quality assurance tester fails t o be present for commissioning testing and sign-off. Neither the tester nor the line manager can be contacted. The team, frequently engaged in similar projects with extensive testing experience,is confident that the facility will perform flawlessly on Monday morning. What should the project manager do?查看答案
试题参考答案:D
试题5
A project is being executed when a few changes are brought to the attention of the team.The changes are needed, but everyone has different opinions on what they think is right. What should the project manager do?查看答案
试题参考答案:A
试题解析与讨论:www.cnitpm.com/st/483568048.html
试题6
项目执行一切顺利,突然因为组织战略的调整而提前终止。发起人要求项目经理记录项目的最终情况,以便向组织汇报并接受组织审计。项目经理应该开始以下哪项工作?()查看答案
试题参考答案:A
试题7
进度网络分析所使用的分析技巧包括下列哪项?查看答案
试题参考答案:C
试题解析与讨论:www.cnitpm.com/st/494226.html
试题8
Which of the following tools or techniques is used to identify internal and external risks for a project?查看答案
试题参考答案:D
试题9
在制订项目进度计划过程中,项目发起人要求项目经理在不造成成本增加的情况下,比原先要求的时间提早交付项目,项目经理应该怎么做?查看答案
试题参考答案:A
试题10
某项目具有具体的服务等级协议,保证向客户提供的服务质量,项目经理可以使用哪项工具来确定服务稳定或具有预期性?查看答案
试题参考答案:A