PMP高频错题(1)
[单选] 在执行阶段,市场部通知项目发起人中心小组提供了看产品的混合审查,需要进行细微变更,项目发起人指示项目经理包含变更,因为该变更不会改变范围或预算。项目经理接下来应该怎么做?
During the execution phase, marketing informs the sponsor that focus groups give the project mixed reviews and a minor change is required. The sponsor instructs the project manager to incorporate the change, because it will not change the scope or budget. What should the project manager do next?
A:记录要求的变更。
Document the requested change
B:为执行变更分配职责
Assign responsibility for implementing the change
C:与受影响方沟通该变更
Communicate the change to the affected parties
D:召集团队来评估变更的影响
Convene the team to evaluate the impact of the change.
正确答案:D 你的答案:A
解析:监控过程组 项目整合管理 实施整体变更控制的流程。
[单选] 一个项目由三个活动组成。A 活动历时 5 周,B 活动历时 6 周,C 活动历时 7 周。活动排序为 A-B-C。但是,活动 B 的资源分配要 1 周,C 在 B 活动开始 1 周后开始。则该项目最短工期是多少?
A project is made of three activities. Activity A is lasting for 5 weeks, activity B is lasting for 6 weeks, activity C is lasting for 7 weeks, the taxis is A-B-C. While, it will take 1 week for resource distribution of activity B, and activity C will start in one week after the beginning of activity B. What is the shortest time limit for this project?
A:12 周
12 weeks
B:13 周
13 weeks
C:14 周
14 weeks
D:16 周
16 weeks
正确答案:C 你的答案:B
解析:PMBOK(6) 6.5.2.2关键路径法。
[单选] 采购订单属于哪一种合同类型?
Which contract type is a purchase order?
A:工料合同
Time and material
B:成本加固定酬金合同
CPFF
C:成本补偿合同
Cost-reimbursable
D:固定总价合同
Firm fixed-price
正确答案:D 你的答案:A
解析:按照规定的价格交付规定的产品的采购订单也是固定总价合同的一种