Upon completion of a project ,the project manager archives the project plan, minutes of the status meetings, regulatory reports, and other project documents, After completing the final project report ,what should the project manager do next?
A、Distribute the final report to the sponsor.
B、Close procurements
C、Obtain acceptance of project deliverables
D、Update the issue log
温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!
相关推荐