The project manager is asked to estimate a project’s costs. The cost and time estimates must be accurate and the detailed cost of every work package is required. Which of the following techniques should be used?
A、Top-down estimates
B、Rough order of magnitude estimates
C、Bottom-up estimates
D、Parametric estimates