在新项目启动会议期间,因为项目将需要采购新设备,生产经理拒绝接受批准的章程。然后项目经理通知项目发起

2021年06月24日来源:信管网 作者:cnitpm

During a new project’s kick-off meeting a production manager refuses to accept the approved charter because the project will require the procurement of new equipment. The project manager then informs the sponsor that the charter failed to include equipment procurement because the production manager was absent.What should the project manager do next?

在新项目启动会议期间,因为项目将需要采购新设备,生产经理拒绝接受批准的章程。然后项目经理通知项目发起人,由于生产经理缺席,章程未能包括设备釆购。项目经理下一步应该怎么做?

A.Review the production manager’s concern with the client.与客户一起审查生产经理关切的问题。

B.Record the production manager’s concern and obtain their support after the kick-off meeting.记录生产经理关切的问题,并在项目启动大会之后获得他们的支持。

C.Conduct another cost-benefit analysis that includes the production manager’s feedback.开展另一项成本效益分析,包括生产经理的反馈。

D.Explain to the production manager that equipment costs will not impact project business value.向生产经理解释设备成本不会影响项目业务价值。

信管网参考答案:C

信管网解析:

C是参考答案。当前阶段处于项目启动阶段,需要关键干系人对于项目章程理解一致。参考章节4.1.1.1B选项在启动大会后获得支持不合适,重大事项需要关键干系人确认后方可执行。

 

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!