2013下半年信息系统项目管理师综合知识真题75:The intention of the()is to schedule, organize and control all activities to achieve the project goal eventually.no matter how difficult it is and what kind of risks are there.
75、The intention of the()is to schedule, organize and control all activities to achieve the project goal eventually.no matter how difficult it is and what kind of risks are there.
A、project work breakdown
B、project security authentication
C、project management
D、project flowchart
参考答案:C