( ) from one phase are usually reviewed for completeness and accuracyand approved before work starts on the next phase.
A、Process
B、Milestone
C、Work
D、Deliverables
一个阶段所产生的可交付物通常要在开始下一个阶段的工作之前对其完备性和正确性进行评审并获得批准。
Organizations perform work to achieve a set of objectives. Generally, work can be categorized as either projects or operations, although the two sometimes are ( ).
A、confused
B、same
C、overlap
D、dissever
组织执行工作以达成一组目标。通常,工作可被分为项目或是运营,虽然两者在某些时候会有所重叠。
In the project management context, ( ) includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.
A、integration
B、scope
C、process
D、charter
在项目管理语境中,“整体”包含了统一、合并、联接的特性,以及对于完成项目、成功满足客人和其他干系人的需求及管理期望至关重要的整体行动。
Project ( ) Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
A、Integration
B、Scope
C、Configuration
D、Requirement
项目范围管理包括为确保项目包含且仅只包含成功完成项目必须工作的所需过程。
On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and ( ) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
A、time estimating
B、cost estimating
C、project planning
D、schedule development
在某些项目,特别是在范较小的项目中,活动排序、活动资源估算、活动历时估算和进度制定连接得如此紧密,以至于它们被视为可以由一个人在相对较短的时间内执行的单独过程。