2016上半年信息系统项目管理师英文题与参考答案
71、After acceptance and formal transfer of information systems to customers it has entered the stage of ()
A、preparation
B、operation and maintenance
C、development
D、extinction
信管网参考答案:B
72、()a method of obtaining early feedback on requirements by providing a working model of the expected product before actually building it
A、prototype
B、object oriented
C、structured method
D、iterative method
信管网参考答案:A
73、The scope management plan is how the team will prepare the()a document that includes
descriptions of create the WBS, verify completion of the project deliverables, and control requests for changes to the project scope.
A.project charter
B.project scope goal
C.project budget
D.project scope statement
信管网参考答案:D
74、( ) is one of the tools and techniques of Sequence Activities
A.Decomposition
B.Fishbone Diagram
C.Precedence Diagramming Method
D.Expert Judgment
信管网参考答案:C
75、The schedule management plan is a component of the project management plan The
schedule management plan may be formal or informal, highly detailed or broadly framed, based upon the () of the project, and includes appropriate control thresholds.
A.goals
B.values
C.needs
D.level
信管网参考答案:C