信息系统项目管理师每日一练(2015-9-8)内容
第1题: ( )are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.
A. Controls
B. Baselines
C. Project stakeholders
D. Project managers
Estimating activity durations uses information on activity scope of ( ), required resource types, estimated resource quantities, and resource calendars.
A. milestone
B. baseline
C. quality
D. work
下表为一个即将投产项目的计划收益表,经计算,该项目的投资回收期是( )。
A.4.30
B.5.73
C.4.73
D.5.30
J2EE的四层体系架构(客户层/表示层/业务逻辑层/数据层)中,可用来实现业务逻辑层的技术是( )。
A.Internet Explore
B.Database
C.Enterprise JavaBean
D.Servlet
甲公司生产急需5000个零件,承包给乙工厂进行加工,每个零件的加工费预算为20 元,计划2 周(每周工作5 天)完成。甲公司负责人在开工后第9天早上到乙工厂检查进度,发现已完成加工3600 个零件,支付款项81000 元。经计算,( )。
A.该项目的费用偏差为-18000元
B.该项目的进度偏差为-18000 元
C.该项目的CPI 为0.80
D.该项目的SPI 为0.90
配置识别是配置管理的一个要素,包括选择一个系统的配置项和在技术文档中配置项目的功能和物理特性()是配置管理的员的关键职责
A、识别软件开发中产生的所有工作结果
B、给每个产品及其组件和相关的文档分配标识
C、定议每个配置项目的重要特征以及识别其所有者
D、修改基线
按照沟通计划安排,项目经理在某财务控制点要根据挣值分析理论向财务总监提交绩效报告,下列绩效报告内容正确的是()
A、按照控制账户中财务指标,对CPI CV BAC进行计算和分析并提出措施
B、根据控制点基线,对CPI CV SPI SV BAC进行计算和分析并提出措施
C、根据控制点基线,对CPI CV SPI SV ETC进行计算和分析并提出措施
D、按照控制账户中财务指标,汇报财务状态、进展报告,进行状态分析
下列关于需求变更影响分析的做法中,()是错误的
A、需求主管人员把需求变更的优先级分为5级
B、建立一个需求决策数据库,根据数据库内容知道变更决策
C、没有代价或不影响进度的变更可以直接实施
D、变更分析流程需考虑:涉及问题核对,影响软件元素核对,评估变更工时、评估工作值总和、任务顺序、变更对路径的影响,对进度成本的影响、优先级等
评估和选择最佳系统设计方案时,甲认为可以采用点值评估方法,即根据每一个价值因素的重要性,综合打分在选择最佳的方案。乙根据甲的提议,对系统A和系统B进行评估,评估结果如下表所示,那么乙认为()
A、最佳方案时A
B、最佳方案时B
C、条件不足,不能得出结论
D、只能用成本/效益分析方法做出判断
()是用于编制沟通计划的输入
A、项目章程
B、沟通管理计划
C、沟通频率
D、沟通术语词汇表