英语试题:Aprojectmanageriscalledtoaninformalmeetingwiththec

2015年07月01日

试题来源:信管网 作者:cnitpm

试题分类:英语

A project manager is called to an informal meeting with the customer and a problem is raised. This problem has major implications for the project manager’s company, but the customer wants to pursue a solutionat the meeting, The project manager should(  ).
A.Tell the customer that he will not address any problems
B.Tell the customer that the problem is not sufficiently defined to company to a solution
C.Collect as much information on the problem without committing hiscompany to a solution
D.Give the customer a range of solutions that might be acceptable to his company