信管网试题分类练习

导航

英语试题(2015-6-12):The earned value technique is a commonly used meth

2015年06月12日

试题来源:信管网 作者:cnitpm

试题分类:英语

The earned value technique is a commonly used method of performance measurement. It integrates project scope, schedule, and cost measures to help the project management team assess project performance. If a project's Cost Performance Index(CPI=EV/AC) value less than 1.0, it means that ( )
A.the cost savings for work completed
B.the project is ahead of its planned schedule
C.the cost overrun for work completed
D.less work was completed than was planned

试题出处:http://www.ruantiku.com/shiti/32011102.html
在下面提交答题后即可查看答案与考友试题分析

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:
请使用浏览器的分享功能,把好文章分享给更多的人

信管网 - 信息系统项目管理专业网站

下载APP-在线学习

培训课程

0元畅享

考试题库

免费资料

APP下载