信管网章节习题

导航

英语试题(2015-2-17):Aprojectmanagerbelievesthatmod

2015年02月17日

试题来源:信管网 作者:cnitpm

试题分类:英语

A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ( )
A. change the scope baseline
B. call a meeting of the configuration control board
C. assign change tasks to project members
D. postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

试题出处:http://www.ruantiku.com/shiti/31011068.html
在下面提交答题后即可查看答案与考友试题分析

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:

信管网 - 信息系统项目管理专业网站

下载APP-在线学习