A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should ( )
A. change the scope baseline
B. call a meeting of the configuration control board
C. assign change tasks to project members
D. postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline