信管网试题分类练习

导航

英语试题(2014-11-6):Youareaprojectmanagerforasmall

2014年11月06日

试题来源:信管网 作者:cnitpm

试题分类:英语

You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you've spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000. According to your schedule, you should have spent ¥300,000 by this point. Based on these circumstances, your project could be BEST described as ( ) .
A、Ahead of schedule
B、Behind schedule
C、On schedule
D、Having not enough information provided

试题出处:http://www.ruantiku.com/shiti/57501980.html
在下面提交答题后即可查看答案与考友试题分析

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:
请使用浏览器的分享功能,把好文章分享给更多的人

信管网 - 信息系统项目管理专业网站

下载APP-在线学习

培训课程

0元畅享

考试题库

免费资料

APP下载