A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should( ).
A.assign change tasks to project members
B.call a meeting of the configuration control board
C.change the scope baseline
D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!
相关推荐
2021/06/16
2021/07/26
2014/11/05
2021/05/20
2014/11/05