On some projects, especially ones of smaller scope. activity sequencing. activity resource estimating. Activity duration estimating, and ( ) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.
A. project planning
B. schedule development
C. cost estimating
D. time estimating
温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!
相关推荐
2022/04/08
2014/09/17
2022/09/24
2022/12/14
2023/03/05