信管网章节习题

导航

英语试题:Theearnedvaluetechniqueisacommonlyusedmethodofperf

2024年02月13日

试题来源:信管网 作者:cnitpm

试题分类:英语

The earned value technique is a commonly used method of performance measurement. It integrates project scope, schedule, and cost measures to help the project management team assess project performance. If a project's Cost Performance Index (CPI=EV/AC)  value less than 1.0, it means that ( )
A. the cost savings for work completed
B. the project is ahead of its planned schedule
C. the cost overrun for work completed
D. less work was completed than was planned

试题出处:http://www.ruantiku.com/shiti/42191453.html
在下面提交答题后即可查看答案与考友试题分析

温馨提示:因考试政策、内容不断变化与调整,信管网提供的以上信息仅供参考,如有异议,请考生以权威部门公布的内容为准!

分享至:

信管网 - 信息系统项目管理专业网站

下载APP-在线学习

培训课程

0元畅享

考试题库

免费资料

APP下载