The IT service manager has learned that a software canimprove the efficiency of current and future project tasks. Because the software is fresh to the Company. Theengineer is not familiar with the software. The lT service manager decides to send the highest level engineero attend the external training course. The proiect manager uses () risk strategies。
A.mitigation
B.enhancement
C.development
D.sharing